ryersonbuilds@ryerson.ca

Student Learning Centre

Transforming the corner of Yonge and Gould streets into one of Toronto’s most vibrant, people-friendly intersections, the Student Learning Centre (SLC) will give the Ryerson community an outstanding environment in which to study, collaborate and share ideas. The SLC was designed through a partnership between two renowned architectural firms: Snøhetta & Zeidler Partnership Architects. It has been targeted to achieve LEED Silver certification. A short video explains the SLC’s main design features.

Status

Construction Stage

What’s Happening

July 28, 2014

With the installation of the curtainwall reaching completion, preparations are being made for the dismantling and removal of the tower crane. This milestone is important since it marks a turning point in the construction process. With the tower crane removed, the majority of the work will be dedicated to the interior spaces.Interior work continues to progress with the metal stud partitioning and drywalling almost completed on all floors. The application of a special sound insulation spray finish has begun on the underside of the concrete ceilings. Tiling for washrooms on all floors  is nearing completion to be followed by the installation of washroom fixtures.

The installation of the elevator rails is ongoing on all five elevator shafts.

Cabling for electrical and data services continues concurrently with mechanical and plumbing line installations.

The roof top mechanical penthouse is now assembled with most of the mechanical equipment in place and the related piping and ductwork infrastructure is moving ahead rapidly.

Preparation of the north wall to receive the insulated metal panels is almost complete. The insulated metal panels are scheduled for installation in September.

The installation of the precast concrete seating along the front entry ramp has begun. This seating also includes a special chamber for the Ryerson SLC time capsule.

View the progress of the SLC here!

 

<

// ]]>

© 2013 Ryerson University | 350 Victoria Street, Toronto, Ontario, Canada M5B 2K3
Rendering of the Student Learning Centre
August 7, 2014
Empty tower crane base.
August 7, 2014
There used to be a tower crane in this opening! Crane removed from site on schedule.
August 5, 2014
Preparing the 600 ton mobile crane to dismantle our tower crane. This process will take all day!
August 5, 2014
More progress on installation of the main lobby acoustic ceiling panels. This is all a part of the dome ceiling structure that will sweep out over the main entrance and up the side of the building. The acoustic panels will dampen noise levels inside the main lobby.
August 5, 2014
There are plants growing on the penthouse roof now!
August 5, 2014
Preparing the 600 ton mobile crane to dismantle our tower crane. This process will take all day!
August 5, 2014
Preparing the 600 ton mobile crane to dismantle our tower crane. This process will take all day!
July 14, 2014
The acoustic panel sections of the Alpolic dome ceiling are continuing.
July 14, 2014
Installation of the plaza precast has begun.
July 14, 2014
Installation of the plaza precast has begun.
July 9, 2014
Main entry stairway in progress. We are preparing for commencement of the precast ramp/ step installation beginning July 10.
July 9, 2014
Air duct risers entering mechanical penthouse.
July 9, 2014
Roof level parapet catwalk structure installation.
July 9, 2014
Main lobby acoustic panel installation in progress.
July 2, 2014
Southeast corner close-in.
July 2, 2014
Southwest corner view showing Phase 7 curtainwall and structural framing for dome panels in progress.
July 2, 2014
Washroom tile in progress.
July 2, 2014
Penthouse roofing membrane prior to green roof installation.
June 10, 2014
Perimeter radiant heating tubes in position on Level 4.
June 10, 2014
Elevator rails and door mechanisms loaded in lobby area.
June 10, 2014
Framing for Phase 13 curtainwall sections to enclose lobby space in progress.
June 10, 2014
Level 5 partition framing in progress.
May 29, 2014
View from the roof top northward. Mechanical penthouse structural steel in progress.
May 29, 2014
Phase 5 curtainwall installation in progress on east wall.
May 20, 2014
Mechanical penthouse structural steel framework installation in progress.
May 20, 2014
Concrete pedestal bases for window washing davit equipment at roof level.
May 20, 2014
I found a big spider in the lobby. He's helping out with ductwork / sprinkler installations.
May 20, 2014
Waterproofing membrane application to main entry plaza in progress.
May 13, 2014
Crane hoisting unitized curtainwall panel to Yonge Street façade.
May 13, 2014
Panel being placed on the Yonge Street façade.
May 13, 2014
Completing final panels for Phase 4 curtainwall scheduled for May 14. Panel being lifted on the Yonge Street façade.
May 13, 2014
Lifting a unitized curtainwall panel from Gould Street onto the building.
May 6, 2014
The final major concrete pour on the structure was completed with the Level 9 roof slab. Photo credits to WSP Canada
May 6, 2014
The next phase of curtainwall installation has begun. Photo credits to WSP Canada
April 24, 2014
Curtainwall on the SLC. Photo credit to WSP Canada.
April 24, 2014
Curtainwall on the SLC. Photo credit to WSP Canada.
April 24, 2014
Curtainwall on the SLC. Photo credit to WSP Canada.
April 24, 2014
Curtainwall on the SLC. Photo credit to WSP Canada.
April 10, 2014
Curtainwall progress.
April 10, 2014
Curtainwall progress.
April 10, 2014
Curtainwall progress.
March 31, 2014
Phase 2 curtainwall has begun!
March 31, 2014
Level 8 concrete pour.
March 31, 2014
Glass panels Loaded on Level 3.
March 31, 2014
General overview showing removal of reshores below Level 5.
March 20, 2014`
Inside the SLC! Photo Credits to Norm Betts.
March 17, 2014
Curtainwall installation on the bridge.
March 17, 2014
Curtainwall installation on the bridge.
March 11, 2014
View nw on Level 7 to elevator core wall rising to underside of Level 8. Note Level 8 slab formwork in progress west of the core walls.
March 11, 2014
View east from Level 3 over atrium stair and bridge. Level 2 bridge slab has been poured and preparations for Level 3 bridge slab in progress.
March 11, 2014
View northeast from Yonge Street. Note re-shoring removal at lower levels of southwest corner of the building. Man and material hoist installation in progress.
March 11, 2014
View to southwest reinforcing steel installation in progress for final Level 7 slab section.
February 19, 2014
View north through Level 1 lobby to north elevator core.
February 19, 2014
View east up atrium stair from Level 1 lobby.
February 19, 2014
View east to café zone.
February 19, 2014
Man and material hoist fabrication underway.
February 19, 2014
Level 7 slab formwork in progress. View southwest.
February 19,2014
Level 7 slab formwork in progress. View northeast.
February 19, 2014
Atrium bridge fabrication continues.
February 3, 2014 - SLC progress
February 3, 2014 - SLC progress
February 3, 2014 - SLC Progress
January 23, 2014 - Curtainwall panel installation in progress
January 16, 2014 - Special structural connection linking sloped columns at the southwest corner of Level 6. Note the sloped steel I-beam with shear studs on all sides to be embedded in the column section. This is a very unusual condition specifically designed to address the structural conditions that will occur at this node.
January 16, 2014 - Spaghetti junction! Electrical condduit and piping sleeves in the Level 6 core area.
January 16, 2014 - Core area slab pour on Level 6. This is the first slab pour section on this level.
January 16, 2014 - Clearing out the ground floor lobby! Shoring in process of removal
December 11, 2013 - Level 5 north core formwork in progress.
December 11, 2013 - View from southwest to northeast building corner. Level 6 cascading formwork in progress,
December 11, 2013 - View south along west side at Level 5.
November 25, 2013 - Student Learning Centre under construction
May 14, 2013 Slab on grade Section 2 is poured.
November 2010 - Demolition
Menu