RTS: March Construction Update

Post 18 of 61

Partitioning for the walls is nearly completed, and will be finished by the end of March. At that point the team will start installing the sound insulation in the walls and then begin the drywalling phase. The ductwork is also being installed this month, along with the electrical rough-ins. Meanwhile, planning is now underway for the move from the current facilities at 44 Gerrard St E to the new space within SLC.