RTS: February Construction Update

Post 22 of 61

Fireproofing of the entire structure has now been completed. The team is laying out the partitions (walls) on the newly-completed floor, a task that is expected to continue until the end of the month. At that point, the mechanical and electrical systems can been installed through the walls and related structures. Meanwhile, the colour palette and entrance marquee have been selected, while faculty and students from Ryerson’s dance program have been testing out options for the sprung dance floor to be installed at a later stage in the project.