June Construction Update

Post 9 of 61

The new ramp within the worksite is now in its final place, and construction of the platform is nearly complete. Once that is done, a concrete footing will be poured, upon which¬† the crane will be erected onsite to complete the remaining soil excavation. This final excavation activity will continue through mid-August; later in the summer a second crane will be erected at the project site. The installation of the final hoarding is in progress, with the balance to be completed once the second crane is in place. The laneway behind the site is now partially closed, with access still available for the church and Ryerson’s loading docks.

Once the cranes are in place and excavation complete, the rest of the year will be spent pouring the concrete for the sub-floors.