If you build it, they will come

Post 45 of 61

August 6, 2014

Mohamed Lachemi, provost and vice president academic, took students on a first-time tour of the Student Learning Centre (SLC). Slated to open in January 2015, recent SLC activity has been on the enclosure of the building. The installation of the exterior curtain wall is on schedule with more than 75 per cent of the panels now in place. The roof top mechanical penthouse is now assembled with most of the equipment in place and the related piping and ductwork infrastructure is moving ahead rapidly. Interior work continues to progress with the ongoing installation of metal-stud partitions and drop ceilings.

http://ryerson.ca/ryersontoday/data/news/2014/08/20140806-If-you-build-it-they-will-come.html