April Construction Update

Post 17 of 61

More than 26,000 cubic metres of soil – or 50 per cent of what is to be removed – has been excavated, with the excavated area now approximately 10 metres below grade. Despite heavy rains in March, project work remained on schedule, and co-ordination with Toronto Hydro, TTC and Enwave continues.

By the Numbers: To date, more than 7,500 work hours have been conducted on the project, and the project has created 20 full time jobs since January 2016.